Should Kitchen Flooring Go in Before or After Cabinets?

It depends on the floor. Tile and nail-down or glue-down hardwood can run under the cabinets, and that order is often the better one. Floating floors, meaning click-together laminate and most luxury vinyl plank, generally go in after the cabinets, because their makers do not want fixed cabinetry pinning down a floor that has to expand and contract. Whichever order you use, two things have to come out right: the finished counter height and the opening the dishwasher slides into.

Floor type Usual order Main reason
Porcelain or ceramic tile Floor first, or at least under every appliance bay Tile adds height that can trap a dishwasher
Nail-down or glue-down hardwood Floor first It is fastened to the subfloor and can carry cabinets
Floating laminate or vinyl plank Cabinets first The floor must move freely, and makers restrict cabinets on top

Tile floors

A tile floor is a stack of underlayment or backer board, mortar and tile. That stack is the thickest of the common kitchen floors, which is why the order matters most here.

If the cabinets go in first and the tile stops at the toe kick, the cabinets sit lower than the walking surface by the full thickness of the stack. The counter ends up that much closer to the floor, the toe kick space gets shorter, and any appliance bay left untiled becomes a shallow pit. A dishwasher in that pit works fine until it needs service. Then it has to be lifted over a tile lip with a countertop directly above it.

Tiling the whole room first avoids all of that and gives you a floor that still makes sense if the layout changes later. The trade-off is paying for tile nobody will see. A middle course is to tile under the dishwasher, range and refrigerator bays and a few inches past the cabinet line, then set the cabinets. Whichever you choose, tile is rarely dead flat, so the installers will still shim and level the boxes.

Nail-down and glue-down hardwood

Hardwood that is nailed or glued to the subfloor is part of the structure under your feet. Cabinets set on top of it do not stop it from doing anything, so running it wall to wall before the cabinets is the common order. A continuous floor means a wider range, a different refrigerator or a reworked island years from now will not expose bare subfloor.

There are two reasons to reverse the order. One is cost, since the flooring under the cabinets is hidden. The other is damage, because a site-finished floor can get scratched while cabinets and stone are being carried in. If the cabinets go first, ask whether the installers can set them on plywood strips that match the thickness of the finished floor. The counter height and the appliance openings then come out the same as if the flooring ran underneath. If the floor goes first, cover it with protection board before the cabinet delivery and leave the covering down until the countertops are in.

Floating laminate and vinyl plank

A floating floor is not attached to the subfloor. The planks lock to each other and the whole sheet grows and shrinks with temperature and humidity, which is why installers leave a gap at the walls. A run of base cabinets screwed to the wall, loaded with stone and standing on that sheet holds it in place at one end.

Manufacturers address this in their installation instructions, and they do not all say the same thing. Pergo's laminate guide tells installers to put kitchen islands and other heavy items in first and keep them off the laminate, so the floor can move around them. Other makers rule out any cabinetry on top of a floating floor. At least one rigid-core vinyl maker allows cabinets on top only if the planks under them, and a margin around them, are fully glued to the subfloor. Because the wording varies and the flooring warranty depends on following it, read the instructions for the exact product before you set the order. The flooring installer and the manufacturer have the final word.

In practice, that means cabinets first for most floating floors. The planks then run up to the cabinet base with the expansion gap left open, and a toe kick cover or shoe molding hides the gap. Ask the flooring installer to carry the planks into the dishwasher, range and refrigerator bays so the appliances stand at finished floor level.

Counter height and the dishwasher opening

Base cabinets are leveled from the highest point of whatever they stand on. The height of the finished counter above the surface you walk on is the cabinet height plus the countertop thickness, minus any flooring that gets added in front of the cabinets afterward. A thin vinyl plank barely changes it. A tile stack changes it enough to notice at the sink.

The dishwasher is less forgiving than your posture. Its installation instructions give a minimum height from the floor it stands on to the underside of the countertop, and its leveling legs adjust only so far. Before any floor or cabinet goes in, compare that minimum with the planned build-up: subfloor, flooring in the bay, cabinet height and countertop. The safe rule is finished flooring inside the dishwasher bay at the same level as the floor in front of it.

If you are still choosing appliances, pick the dishwasher model before the cabinets are ordered. Your designer can then check the opening against the real specification sheet. The same thinking applies when you measure the kitchen for cabinets: note the floor type and its thickness along with the wall dimensions.

Getting appliances out later

Ranges and refrigerators come out more often than cabinets do. A slide-in range has to clear any lip at the front of its bay, and a refrigerator rolls on small wheels that stop at a flooring edge. Flooring that continues under every freestanding appliance, at one level, is what lets a service call or a replacement happen without anyone touching the countertop.

The same foresight helps with utilities. If an island needs power or plumbing, the conduit or pipe goes into the floor before the finish flooring and before the island cabinets, as described in the article on planning electrical for a kitchen island. In an older house, an out-of-level subfloor should be dealt with first, and our piece on fitting new cabinets in an older home covers what that involves.

Questions that come up on site

Can a kitchen island sit on a floating floor?

Treat an island like any other fixed cabinet. It is anchored to the subfloor and carries a stone top, so the flooring instructions described above apply to it. The usual approach is to set the island first and run the floating floor around it with the required gap.

Can new flooring go over the old floor while the cabinets stay?

It can, but every layer added in front of the cabinets lowers the counter relative to the floor and raises a lip in front of the dishwasher. Pull the dishwasher, floor its bay to the same level, and check that the opening still meets the minimum height in the appliance instructions before you commit to the thicker floor.

When does the toe kick trim go on?

After the floor. The finished toe kick cover and any shoe molding are the last pieces, because they hide the cut edge of tile or the expansion gap of a floating floor. Tell the cabinet installers which floor is coming so they leave those pieces off, or leave them loose, until it is down. The cabinet installation checklist lists the other things to have ready for the crew.

Decide the floor before the cabinet order

Flooring type and thickness belong in the design conversation, well before installation week. Bring them to a 3D design appointment at Aqua Kitchen and the designer can plan tall cabinet heights, toe kicks and appliance openings around the finished floor. You can look through the cabinet collections beforehand, and the guide to the order of work in a kitchen remodel shows where flooring sits among the other trades.